Quick answer: A grenade transport case quote only becomes comparable after it is split into tooling, per-unit conversion and freight. Minimum order quantity follows from cavity count and changeover time, and lead time runs backward from drawing freeze.

Table of contents

  • Three Cost Blocks in a Quote
  • Per-Unit, Per-Kilo and Per-Hour Pricing
  • MOQ and the Mould Cycle Break-Even
  • Lead Time Counted Backward
  • RFQ and Payment Milestones
  • FAQ

1. Three Cost Blocks in a Quote

A single line reading 160 yuan per unit hides where the money goes. Split a grenade transport case purchase into one-time tooling, per-unit conversion and freight; only conversion scales with volume, so a blended figure lets either side bury margin.

For a 5.2 kg finished case, one mould costs 42,000, sampling 3,000 and testing 1,800. The 46,800 total lands at 78 per unit across 600 pieces and 19.5 across 2,400.

BlockContentsBasisRoom to negotiate
One-timeMould, samples, revision, reportPer projectShared tooling, fewer cavities
Per-unitShot weight, cycle, assembly, packingPer piece, falling with volumeThinner non-structural ribs
FreightTrucking, customs, oceanPer container and laneConsolidated loads

2. Per-Unit, Per-Kilo and Per-Hour Pricing

The same grenade transport case body can be quoted per piece, per kilo or per machine hour, and the readings diverge by 18 percent. Per-piece hides tooling amortisation in the unit price.

Per-kilo fails on gross versus net: some multiply finished weight by resin price, others take gross weight plus 8 percent regrind loss, and masterbatch on dark parts runs 2 to 3 percent.

Per-hour is transparent but hard to check. A 1,000 tonne press on one cavity at a 205 second cycle yields about 0.057 machine hours per case; quote 260 seconds and labour grows by a quarter.

3. MOQ and the Mould Cycle Break-Even

Minimum order quantity is derived, not announced. A grenade transport case mould costing 42,000 lasts about 250,000 shots, so one cavity would need a quarter of a million pieces to wear out. Changeover is the real cost line: each swap plus first-article approval takes 90 minutes of press time the batch absorbs.

That puts single-cavity break-even at 600 pieces. Below it setup cannot be spread; above 2,400 the marginal gain flattens and further cuts must come from resin.

Volume bandUnit priceTooling per unitDelivery
600 pcs1867842 days
1,200 pcs1583938 days
2,400 pcs14119.535 days
5,000 pcs1339.433 days

4. Lead Time Counted Backward

Lead time on a grenade transport case starts the day the drawing is frozen. Put that in the contract, or two weeks of revisions get counted as production and the shipment lands half a month late.

Count backward on 2,400 pieces: steel day 7, first trial day 18, second trial day 26, production day 34, 380 pieces a day finishing in 6.3 days, inspection 3 days, customs 5 days, ocean 18 days. The path runs 66 days, so write 72 with five days of buffer.

MilestoneDayPreconditionUsual delay
Drawing freeze0Signed 3D fileCavity changes
Steel and base7Tooling paymentBase misfit
First trial18Flow analysis passedSink marks
Second trial26First-article reviewLatch fit off
Production34Resin on sitePress conflict
Inspection and loading43Sampling planBatch fails

5. RFQ and Payment Milestones

A specific RFQ returns comparable numbers: drawing and revision, resin grade, colour code, shot weight, insert format, printing, packing, volume band, delivery point. Leave one blank and the supplier fills it with a default.

Tie payments to deliverables: thirty percent at signature releases tooling, forty after the trial sample is signed, thirty after inspection clears the batch.

Five clauses belong in the contract: mould ownership transfers to the buyer, inspection at AQL 1.5, late delivery at 0.5 percent per day capped at 10 percent, a 45 day quote validity, and a price review past an 8 percent resin index move.

Conclusion

Procurement of a grenade transport case comes down to three tables: cost split into blocks, volume into bands, lead time into milestones with a five day buffer. Align them before arguing about unit price, then lock mould ownership and inspection criteria into the contract. Bought this way, a grenade transport case can be reordered without restarting the negotiation.

This article discusses only the container (case body) side of specifications and design intent, and does not cover any handling, loading or use of the contents.

Related Reading

Related Products