Quick answer: An injection molding plastic case factory should quote in six lines: resin, machine time, tooling, packing, tax and freight. MOQ follows press tonnage and cavity count, and lead time splits into tool, trial and production. An 800 × 600 × 400 mm body tool runs 180,000 to 260,000 RMB, a single-cavity first order starts at 300 units, 35 days first run, 15 repeat.

Table of contents

  • How an Injection Molding Plastic Case Factory Prices a Case
  • Amortising the Tool Into the Unit Price
  • MOQ Follows Press Tonnage and Cavity Count
  • Three Segments of Lead Time and the Buffer
  • Factory Audit and Payment Milestones
  • FAQ

1. How an Injection Molding Plastic Case Factory Prices a Case

A single-number quote leaves nothing to negotiate. The same drawing returns at 78 RMB from one injection molding plastic case factory and 96 from another, with the gap in resin grade, regrind ratio and tooling, not in moulding.

Resin first: a 2.8 kg body draws about 3.1 kg of compound with runners, and capping regrind at 15 rather than 30 percent moves the price 4 to 6 RMB. Machine time is rate times cycle, so a 1000-tonne press at 180 RMB per hour on a 95-second single-cavity cycle lands at 4.75 RMB.

LineBasisRange
Resinnet weight plus scrap18 to 24 RMB per case
Machine timerate × cycle4 to 7 RMB per case
Toolingone-off or per unit180,000 to 260,000 RMB

2. Amortising the Tool Into the Unit Price

Tooling is the softest line in any injection molding plastic case factory quotation. An 800 × 600 × 400 mm body needs cavity, core, sliders and cooling circuit, at 180,000 to 260,000 RMB, the spread coming from mould base steel and hot runner choice. Ask who owns the tool, how many shots it lasts and who pays for repairs.

Injection molding plastic case factory: corner of a scuffed black case with one square latch closed, wooden crates and coiled cables behind, concrete floor
Injection molding plastic case factory: corner of a scuffed black case with one square latch closed, wooden crates and coiled cables behind, concrete floor

Amortised over 3,000 units, a 200,000 RMB tool adds 67 RMB per case; over 300 units it adds 667. Below 1,000 units the tool belongs on its own line. Write the life down as well: P20 steel washes out near 200,000 shots, 718H holds past 300,000.

3. MOQ Follows Press Tonnage and Cavity Count

The minimum is not arbitrary. It is press tonnage, cavity count and purge cost added together. Bringing a 1000-tonne barrel to 220 °C costs 90 minutes of power with no output, and first-off approval burns 15 to 25 cases while wall and flash settle.

A colour change adds 8 kg of purge and two hours with the screw drawn. Spread over 200 units, real cost reaches 1.6 times the quoted price, which is why a single-cavity tool quotes from 300 units, a two-cavity from 500 and a colour change from 500.

4. Three Segments of Lead Time and the Buffer

The 35 days split into 22 of tool making, 5 of trials, 6 of production and 2 of loading; a repeat skips the tool and ships in 15. Buffer sits in resin ordered 7 days ahead and in three trial rounds two days apart.

Injection molding plastic case factory: open black wheeled case standing on the floor, grey lid foam, compartmented base foam, two casters and side handles
Injection molding plastic case factory: open black wheeled case standing on the floor, grey lid foam, compartmented base foam, two casters and side handles

Peak season adds 10 days from September to November. A 40HQ holds 480 cases at 0.62 cubic metres and booking runs 14 days ahead, so commit to the loading date, not completion.

SegmentFirst orderRepeat
Tool making22 days0
Trials5 days0
Production6 days13
Packing and loading2 days2

5. Factory Audit and Payment Milestones

Skip the showroom: the tonnage plate on each press, the tool store and the resin batch log settle an audit. Pay 30 percent to release the tool, 60 before shipment and 10 after inspection, with tooling at 50/50 around a passing trial, so a failed trial still leaves leverage.

Write three clauses: a quarterly resin index with a ±5 percent trigger, damages of 0.3 percent per day capped at 5 percent, and AQL 1.0 lot release.

Conclusion

Procurement from an injection molding plastic case factory comes down to three tables: cost breakdown, MOQ matrix, lead-time split. The first shows where money goes, the second whether volume can drop, the third who caused a delay. Attach all three and an injection molding plastic case factory that signs them can hold a date.

This article discusses only the container (case body) side of specifications and design intent, and does not cover any handling, loading or use of the contents.