Quick answer: Settle an order change quantity first and colour second: volume fixes how many clean-outs the press needs, shade only fixes what runs through it.

Table of contents

  • Lock Quantity Before Colour
  • Adding Volume: the 10 Percent and 30 Percent Lines
  • Recolouring: 90 Minutes and 3 kg
  • A One-Page Change Note and a 24-Hour Reply
  • FAQ

1. Lock Quantity Before Colour

Two order change requests often land on one order: more units, and another shade. Volume sets how many times the press is cleaned; shade only sets what runs through it. Fix the shade first and the press runs two clean-outs for one colour, 90 minutes and 3 kg of scrap each time.

So the first step of any order change is to freeze the quantity: the total, the split, and the latest collection date for the last batch. Only then does a shade mean anything, because it decides how many segments the batch is moulded in.

The freeze window is the hard edge, 7 days before production starts. Inside it a change may only touch what is not yet scheduled; outside it, the change is rescheduled as a new order. When volume and shade arrive together, judge the volume band first and the colour panel second, or the schedule is recalculated twice at half a day each.

Change typeInside the 7-day freezeOutside the freeze
Volume under 10%No reschedule, absorbed by the batchFolded into the running batch
Volume 10% to 30%One night shift, date unchangedFolded in, 1 to 2 days later
Volume over 30%Reschedule, date recalculatedScheduled as a new order
Recolour, same family7 days later, 1 clean-out7 days later, may share a clean-out
Recolour, new family14 days later, 2 clean-outs14 days later, separate segment

2. Adding Volume: the 10 Percent and 30 Percent Lines

An order change that adds volume is judged by size before price. Under 10% inside the freeze, the schedule does not move. Between 10% and 30%, one night shift closes the gap. Above 30%, cavities and cycle time cannot keep up. So the order is rescheduled. The line is arithmetic: a four-cavity tool at 90 seconds a shot makes a fixed count in 24 hours, and the rest queues.

Order change on the floor: two stacks of closed black cases on a green bench mat, red latches along the sides, yellow pegboard behind
Order change on the floor: two stacks of closed black cases on a green bench mat, red latches along the sides, yellow pegboard behind

Step pricing is the half most buyers miss. Moving from 300 to 500 units cuts 6%, and 500 to 1000 cuts 11%. An order quoted at 480 units that grows to 520 belongs in the 500 band; keep the 480 price and the 6% vanishes quietly.

Volume addedRescheduleDelivery effectPrice band
Under 10%NoUnchangedCurrent band
10% to 30%One night shiftUnchanged or +1 dayNew band if crossed
Over 30%Yes+7 days and upRequoted

Volume also pulls on material already issued. Same colour and grade, and the top-up takes 2 days; batch already moulded, and the extra units need a fresh issue and drying cycle, neither of which sits on the schedule after an order change.

3. Recolouring: 90 Minutes and 3 kg

A recolour costs cleaning time, transition scrap, and a new colour panel. Clearing the hopper, screw and hot runner takes 90 minutes, and material between the first shot and a stable shade counts as 3 kg of scrap. Dark to light needs two clean-outs, 180 minutes and 6 kg.

Colour reaches back into material already issued. Pigmented pellets cannot return to natural, so the mixed portion is written off at 85%, with 15% kept for blending into the same family.

Recolour caseClean-outsScrap, kgSlip
Same family, lighter or darker13+7 days
Dark to light26+7 days
New family, olive to orange26+14 days
After material issue26+14 days, plus 85% write-off

A colour panel is not mixed on the spot; it is re-shot and signed off in writing. Pale material is far more sensitive to a shade difference, so approval takes twice as long. Running before the signature produces the wrong shade, and reworking a batch costs more.

4. A One-Page Change Note and a 24-Hour Reply

The order change note is one page and five columns: change type, original value, new value, days lost, and who carries the cost. Anything beyond those columns is a remark, and remarks never reach the system. The cost column is left blank most often, and a blank column turns reconciliation into two versions of one story.

Order change at the press: a green conveyor carries freshly moulded black cases while an operator in a navy polo checks a clipboard
Order change at the press: a green conveyor carries freshly moulded black cases while an operator in a navy polo checks a clipboard

Set the reply window at 24 hours. No answer in 24 hours means the original order stands, and that sentence belongs in the contract, or every order change becomes a negotiation. The window protects the only slot left: with 7 days of freeze, a three-day reply leaves four.

Two free changes per order, then a fixed fee. The allowance is not permission to keep editing; it separates small edits from structural ones. The first two are usually a few dozen units or another shade. The third usually means the design is unsettled, and a fee settles that faster than an argument.

Put the freeze and the note into the contract together: 7 days before production is frozen, a recolour is +7 days and a new family +14 days, replies come in 24 hours, and each order carries 2 free changes.

Conclusion

Order change management is a sequence: freeze the quantity, settle the shade, write it into a one-page note. Quantity is fixed before the 7-day freeze, volume runs along the 10% and 30% lines, and shade is settled before material is issued, so the 90-minute clean-out and the 3 kg of scrap are paid once. In that order it is arithmetic; backwards, it is an argument nobody wins.

Related Reading

Related Products