Quick answer: Ramp up runs on three separate curves, yield 88% to 97.5%, cycle 68 s to 62 s, output 45% to 92% of target, and four bottlenecks sit outside the press.

Table of contents

  • Month one: 88% yield at 68 seconds
  • Cooling, and the 8 seconds it costs
  • Six die changes in the first month
  • Foam five days late, and the 100% inspection
  • What you can promise in month three
  • FAQ

1. Month one: 88% yield at 68 seconds

The target was plain: 30,000 cases a month, 62 s a part, one press, two shifts over 26 days. Month one closed at 517 parts a day, 45% of target. Nothing was broken; the numbers had not converged.

Yield sat at 88%, so 12 parts in every 100 were scrapped or reworked. Cycle ran 68 s, 6 s over design. Multiply the two, take off stoppages, and output lands at 45%. Scrap was 4.2% in month one and 1.1% by month three.

A ramp-up curve is not a straight line: the cycle and inspection rules set in the first 30 days carry to day 90, and changing them later costs more than a new tool.

MonthYieldCycleOutput vs targetScrap
End of tooling82%72 s09.0%
Month 188%68 s45%4.2%
Month 294%64 s72%2.3%
Month 397.5%62 s92%1.1%
Month 698.2%61 s98%0.8%

Output climbs 27 points from month one to month two and 20 from month two to three. The steep part of a ramp-up sits in the first 60 days.

The 45% breaks down into 21 h of die changes, 3 days waiting on material, inspection queues and trial modifications, all worth writing down by the hour.

2. Cooling, and the 8 seconds it costs

The shell is 2.8 mm thick and weighs 2.6 kg. With the fixed half at 45 °C, water in at 12 °C and 8 L/min, cooling needs 30 s before the part ejects flat. That is 8 s over design. Cycle slides 60 s to 68 s. That is a water circuit problem, not a press problem. Heat that cannot leave is waited out, at 8 s of power per case and 70 parts a day.

Ramp up review: navy case open on a grey steel shelf, waffle foam under the lid, black foam blocks inside, two black latches, racking behind
Ramp up review: navy case open on a grey steel shelf, waffle foam under the lid, black foam blocks inside, two black latches, racking behind

Three fixes, cheapest first: one baffle set in the core, water from 12 °C to 10 °C, flow from 8 to 10 L/min. All three bring cooling to 24 s and cycle to 64 s, which is where month two came from.

Mould temperature is checked weekly at 3 points: fixed half, moving half, slide. A spread above 5 °C means a blocked circuit, and parameter tuning will not fix it.

Warped corners are the symptom: lift above 0.6 mm at the base makes a case rock on a pallet; it appeared 3 times in month one, each below 26 s.

Cooling is the first bottleneck in most ramp-ups: it never shows on a drawing, only on a stopwatch.

3. Six die changes in the first month

Steady production pulls a tool once a month. Month one pulled it 6 times: 2 trial modifications, 2 customer batches of 300 and 800, 1 material change, 1 unplanned.

At 3.5 h a change that is 21 h, nearly a production day, or 1,000 parts.

Die changes are the easiest capacity to miss: schedules count press hours, never the 3.5 h of stripping and first-off checking.

Night shift, a preheat stand 4 h ahead, staged lifting gear. Month two ran 3 changes, month three ran 1, which is when 62 s became repeatable.

Ramp-up changes scale inversely with batch: 6 changes over 300 parts cost 0.07 h each, over 1,500 parts 0.014 h.

4. Foam five days late, and the 100% inspection

Insert sampling took 12 days and production 8, so foam landed 5 days after the shells. Finished cases sat in dispatch with nothing to ship: zero output.

The second bottleneck was the standard. With no agreed judgement, month one inspected everything: appearance, dimensions, air tightness, 90 s a case, 3 inspectors over 8 h, a ceiling of 960 a day. That held at 517 and queued at 828.

Ramp up assembly floor: green epoxy floor, white framed line, blue board reading assembly group one, operators seated along it, black cases stacked
Ramp up assembly floor: green epoxy floor, white framed line, blue board reading assembly group one, operators seated along it, black cases stacked
BottleneckAppearsCostRelease action
Insufficient coolingWeek 1Cycle +8 s, 70 parts a dayBaffles, colder water, more flow
6 die changesAll month 121 h down, 1,000 partsNight shift, 4 h preheat
Foam lateWeek 3First batch 5 days lateOrder insert with the shell
No inspection standardMonths 1–290 s a part, 960 a dayJudgement card, then sampling

Two of the four sit off the press; when a ramp-up stalls, those clear faster than parameter work.

5. What you can promise in month three

Batches went out at 300, 800 and 1,500, not from caution but to leave room to correct the cycle and the inspection. The 300 proved assembly and packing, the 800 proved 5 stable days, only the 1,500 shipped on normal lead time.

Presses per operator moved 1 to 2, then 1 to 3: month one needed 2 people per press, month three ran 3 presses per operator. That ratio reads progress, not a target.

WeeksInspectionPresses per operatorCommitted batch
1–2100%1 to 2300 cases
3–6100%1 to 2800 cases
7–1050%1 to 31,500 cases
11–1320%1 to 3At 92% of target

Quote lead times against the month's output ratio, never 100%: 45%, then 72%, then 92%. Lead time follows the same ladder, 45 days, 40, 35, so one date in a quotation cannot survive a ramp-up.

The expensive mistake is selling steady-state capacity against ramp-up output.

Conclusion

Ramp up is not a matter of press hours. Yield moves 88% to 97.5%, cycle 68 s to 62 s and output 45% to 92% on one schedule while cooling, die changes, late foam and an undefined standard are cleared. Quote against the month's real ratio and the quarter stays a quarter.

This article covers case-side specifications only and does not address any handling, loading or use of the contents.

Related Reading

Related Products