Quick answer: What Information Is Needed for an Industrial Case Quote is short: inner L/W/H, a 3 mm wall, IP67 at 1 m for 30 min, 100 units and 20 days.

Table of contents

  • Which Three Dimensions to Measure First
  • How Far the Protection Rating Has to Go
  • Describing the Foam Layout in Words
  • Giving Quantity and Delivery Rhythm
  • Which Missing Inputs Slow the Quote
  • FAQ

1. Which Three Dimensions to Measure First

The more an RFQ email reads like a table, the closer the returned price sits to the real cost. The first cell is the inner size, length, width and height taken at the smallest clear space inside the case. Terminals, handles and the widest point belong in that set, and any bulge at a rib is recorded at its tightest point.

What Information Is Needed for an Industrial Case Quote usually fails here. Outer size alone makes the supplier guess a wall before deriving the cavity; 3 mm or 6 mm shifts it by 6 mm, and foam and price shift with it. Inner size plus two walls gives the outer size, so the arithmetic is the supplier's, but the numbers must let it run.

Orientation matters as much as the three figures. Lying flat or standing on end gives a different support face, and the internal ribs move with it. One line putting the long edge along the lid opening replaces a sketch with no direction, and What Information Is Needed for an Industrial Case Quote should then carry the usable clearance, not the largest outline.

2. How Far the Protection Rating Has to Go

IP67 says two things only: immersion to 1 m for 30 min under IEC 60529 and GB/T 4208-2017. It covers neither jet spray nor repeated soaking, so saying so keeps an unnecessary seal out of the price. What Information Is Needed for an Industrial Case Quote should state which condition is being bought.

What Information Is Needed for an Industrial Case Quote black foam cavity cut to tool profile inside yellow case wall, clean edges
What Information Is Needed for an Industrial Case Quote black foam cavity cut to tool profile inside yellow case wall, clean edges

The rating can be written two ways, and they land at different prices. Designed to IP67 means the supplier builds the structure and ships; tested to IP67 adds specimens and an outside test on its own line. Neither is wrong; the bare word waterproof is.

Seal values belong in the same cell: a TPE gasket at Shore A 50–60 and latch retention of 200–400 N decide whether the lid closes onto a compressed seal. For a device rated -20 to 60 ℃, say whether a breather valve is wanted.

Rating wordingDuty it coversDifference in the quote
Designed to IP67short immersion, rain, washstructure and seals only
Tested to IP67acceptance that needs a reportspecimens and outside test
Waterproof, no ratingcannot be judgedsupplier adds margin

Skip the cell and the quote opens at the highest rating, then trims after the drawing is confirmed. What comes off becomes room for negotiation, not money returned.

3. Describing the Foam Layout in Words

A photograph cannot replace words for the foam layout. It shows the device, not the cavity depth, layer count or where the hand goes. EVA at 25–45 kg/m³ with compression set of 10% to 20% decides whether the foam springs back after a press.

What Information Is Needed for an Industrial Case Quote describes the layout in three ways: cavity cut to the outline, a grid of pockets, or egg-crate foam in the lid. The choice depends on whether the shipment is one unit or a set. One unit takes a cut cavity; a tool set takes labelled pockets.

Three things must follow: layer count, depth per cavity, and the side where fingers lift the foam. A wrong depth presses foam onto a panel, and a missing lift point leaves the user picking at the foam edge.

Layout wordingFigures it must includeEffect on price
Cut to outlinecavity depth, clearance, lift pointpriced by cutting time
Pocket gridpocket count, depth, facingpriced by count and die
Egg-crate lidpitch, compressionpriced as a full sheet

Two revisions mark this line. Revision 1 fixes the envelope and cavity positions, revision 2 locks the foam cuts and lift points, and the quote is built on it. Anything later is a change order.

4. Giving Quantity and Delivery Rhythm

What Information Is Needed for an Industrial Case Quote puts 100 units and a 20 day lead time in one sentence, because either alone says nothing. The clock starts when revision 2 is confirmed, and lot size decides material and scheduling.

What Information Is Needed for an Industrial Case Quote black case open, yellow latches, foam holding screen, cable and battery
What Information Is Needed for an Industrial Case Quote black case open, yellow latches, foam holding screen, cable and battery

Delivery rhythm means one shipment or several. For 100 units at once, packing follows a 1200×800 mm pallet and a 40HQ of 12.03×2.35×2.39 m internally, so the count per container is settled before freight costs more than the case.

Split delivery needs a count and an interval for each lot. What Information Is Needed for an Industrial Case Quote often records this as monthly pickup, which leaves restocking and a single run indistinguishable; the price then assumes one batch.

Load rating is the last line: 25 kg per case. Capacity is not unit weight, and ribs, handles and base plate follow the load, so leaving it out hides a bent base until the sample.

5. Which Missing Inputs Slow the Quote

A missing input never makes a quote cheaper, only slower. Without inner size the supplier adds clearance; without a rating the seal goes to the highest grade; without a foam layout the sheet is priced whole.

Missing itemWhat the supplier doesEffect on the price
Inner sizederives cavity from outer boxmargin widens, price rises
Protection ratingseals to the highest gradeunused structure added
Foam layoutprices a whole sheetcutting time unverified
Quantity and deliverycosts the smallest batchunit price up, date vague

Quote check: an RFQ giving outer size only, with no protection rating and no foam layout, usually returns a price off by more than 20%, and that RFQ goes back for missing inputs. The line keeps rework cost before the quote.

Once the list is complete, quotes become comparable: two suppliers working from one table differ on process and material, not on assumed clearance. What Information Is Needed for an Industrial Case Quote is answered fastest as six rows sent once.