Quick answer: A Case Export Packaging quote is comparable only when split into six lines (unit price, mold, packing, palletising, inspection, freight) and tied to four terms: MOQ, mold ownership, lead time trigger, payment schedule.

Table of contents

  • Split the Quote Into Six Lines
  • MOQ and Mold Ownership First
  • Where the Lead Time Clock Starts
  • Payment Terms and Milestones
  • Audit and Sampling in the Right Order
  • Five Traps That Hide in a Quote
  • FAQ

1. Split the Quote Into Six Lines

A Case Export Packaging total says nothing about where the money went. Two plants both quote 68 yuan per unit, one hiding 3 yuan in stretch wrap and the other in tooling, so split the lines.

Unit price carries 78% to 85% of the total, molds are one-off at 48,000 to 120,000 yuan, packing runs 2.5 to 4 yuan per case, and a 1200 by 1000 mm pallet adds 18 to 26 yuan.

Inspection and paperwork get folded into a price, a phrase that says nothing: third-party inspection bills 1,200 to 1,800 yuan per inspector-day, certificates 200 to 400 yuan per shipment.

LineBasisRangeWhere it hides
Unit pricePer case78% to 85% of total13% VAT called inclusive
Mold and jigsOne-off, per set48,000 to 120,000 yuanAmortised, never refunded
PackingPer case2.5 to 4 yuanCorner board cut 5 mm to 3 mm
PalletisingPer pallet18 to 26 yuanCount taken from theory
InspectionPer day, per lot1,200 to 1,800 yuanWritten as included
FreightPer containerMoves monthlyCheap booking, later surcharge

2. MOQ and Mold Ownership First

MOQ sets the steps. Between 300, 500 and 1,000 units a Case Export Packaging price falls 8% to 12%, a gap that comes from changeover, not resin.

Case Export Packaging: a black lid on a white case body from behind, six hinge blocks in a row, latches folded at the sides
Case Export Packaging: a black lid on a white case body from behind, six hinge blocks in a row, latches folded at the sides

Ownership of a Case Export Packaging mold needs a clause. P20 and 718H steel differ by 12,000 yuan and a case mold runs 60,000 to 150,000 yuan, so name the mold number, the plant and a 30-day handover window. Buyer-owned is not enough: who pays the crane, the freight basis and the hours to free steel from a press stay open.

Trial shots should not count toward the delivered quantity, and bulk against one case per carton differs by 4 to 7 yuan.

3. Where the Lead Time Clock Starts

Thirty-five days without a trigger is not a commitment. The chain has five stages.

StageDaysTriggerBottleneck
Trial and approval7 to 12Drawings and chip signedChip couriered 3 times
Material5 to 8Deposit receivedNamed grade out of stock
Moulding12 to 18Mold on the pressPress taken by a bigger job
Assembly4 to 6Parts in houseLiner 2 days late
Booking7 to 10Shipping plan fixedPeak-season space

Add them and you get 35 to 54 days, so the 35 on a Case Export Packaging quote usually stops at packing. Ask which milestone it reaches. A November sailing wants space booked first, with production in parallel to save 5 days. One press running two models with a 45-minute changeover six times a week loses 4.5 hours, so read the order book: below 1 press per 3 open orders, dates slip.

Penalties of 0.3% a day capped at 5% mean little; a missed vessel costs 7 days plus fees beyond the penalty.

4. Payment Terms and Milestones

A Case Export Packaging schedule of 30% deposit and 70% on the bill of lading copy is fair when the deposit pays for material and tooling, not a cash gap.

Case Export Packaging: a white lid open on a black case body, empty cavity up, two latches raised, a handle cut-out in the lid
Case Export Packaging: a white lid open on a black case body, empty cavity up, two latches raised, a handle cut-out in the lid

Two levers move it: the deposit ratio and the balance trigger. Cutting the deposit to 20% lifts the price 1.5% to 2%; moving the balance to 15 days after loading costs 0.7% once 45 days at 6% funding is priced in.

A letter of credit is not automatically safer: 0.15% to 0.3% in fees plus 50 to 80 dollars per amendment, so under 1,000 units a bank transfer wins. Statement by the 5th, payment within 10 days of sign-back.

5. Audit and Sampling in the Right Order

Audit a Case Export Packaging plant before production, sample after the mold is cut; reversed, the sample passes while capacity fails. Four items matter: press tonnage and count, mold library, metrology, packing station.

Two people for three days is the export norm. A 600 by 400 mm projected area needs 850 to 1,200 tonnes of clamping force, so a plant with fewer than 3 presses in that band queues in peak season.

The white sample proves a 3.5 mm wall, the colour sample proves shade within a ΔE of 1.5, and 800 to 1,500 yuan per sample is credited back above 500 units.

Sign the sample. A verbal yes is not a reference.

First-article inspection covers 5 units, a 1.2 m drop on six faces and 3 minutes of IP65 jetting; stop the line on a failure rather than ship it among 1,000 units.

6. Five Traps That Hide in a Quote

In a Case Export Packaging quote, tax comes first: a line marked inclusive with no rate moves the real price 3% to 5%. Pallet count second: a 40-foot high cube holds 320 cases by bare volume and 288 palletised, so the buyer absorbs the missing 32.

TrapSymptomAsk for
Vague taxInclusive, no rateA 13% VAT invoice
Pallet countCapacity from bare volumeLoad plan
Mold in priceLow price, no refundTooling as its own line
Inspection includedFee billed laterInspector and man-days
Open lead time35 days stops at packingDelivery point

A mold folded into the unit price, inspection marked included, a lead time with no anchor: words on the page, no milestone behind them.

Packing loss stays invisible: cartons carry 2% spares against 1.2% to 1.8% actual damage, a supplier margin not worth chasing, but the spare count belongs in the contract.

Conclusion

The work sits in structure, not haggling: six lines separated, tooling outside the unit price, MOQ walked in steps, lead time anchored at both ends, payment pinned to a date. Then a Case Export Packaging quote compares across suppliers and can be signed.

This article discusses only the container (case body) side of specifications and design intent, and does not cover any handling, loading or use of the contents.