Quick answer: Three quotes for one drawing came in at 268, 312 and 371 yuan, a spread of 38%. The gap sits in how each vendor splits the quote: tooling, order quantity, wall thickness and hardware grade, lead time buffer, and the cash cost of payment terms.
Table of contents
- Breaking the quote into five lines
- MOQ and tooling: who owns the mould
- Sampling and the factory visit in two days
- How thirty days split into five milestones
- Payment terms and three sources of a low price
- FAQ
1. Breaking the quote into five lines
Three Equipment Protection Case quotes for one drawing came in at 268, 312 and 371 yuan. Split each into the same five lines before comparing totals, because the 103 yuan gap sits in four places, only one of them the box.
| Line | Share | Driven by | Room to move |
|---|---|---|---|
| Resin | 35% to 45% | Wall and unit weight | Little |
| Moulding | 20% to 25% | Cavities and shifts | Medium |
| Tooling | 5% to 15% | Who holds the mould | Large |
| Hardware and foam | 8% to 12% | Latch, valve, foam grade | Large |
| Packing and freight | 10% to 18% | Volumetric weight | Medium |
Resin is the line to read first. On a 12.6 kg unit, walls going from 4.2 mm to 3.6 mm remove about 0.9 kg, roughly 40 yuan, and the 268 yuan offer was that thin-wall option.
Weigh the samples first.
2. MOQ and tooling: who owns the mould
Fifty units and five hundred differ by 60 yuan a piece, because changeover and heating spread across fewer pieces.
Tooling hides the money. Six questions:
- Billed separately or folded into the unit price
- Who owns the mould, in writing
- Which plant stores it, and who may inspect
- Modification charged per change or per hour
- Quantity tiers at 50, 200 and 500
- Refurbishment at end of mould life
A mould costs around 38,000 yuan: 76 yuan a unit across 500, 760 across 50. Pay for it without recording ownership and the next supplier cuts another one, so the money is spent twice.
Write storage location and inspection access into the clause, or the mould belongs to the holder.
3. Sampling and the factory visit in two days
Sample approval covers wall thickness, latch force and foam fit. A failed first article ends the discussion.
Day two is the visit: three records and one line. Machine checks, incoming resin, first-article inspection, plus moulding machine, mould rack and bench on one site. Records that miss the floor were written afterwards.
Salt spray for an Equipment Protection Case is usually quoted at 96 hours, and hardware plating needs its own confirmation. Two vendors' latches on one bench means mixed parts, the usual by-product of a cheap order.
Ask the supervisor three things: output per cavity, colour change time, reason for the last rework.
4. How thirty days split into five milestones
Thirty days for an Equipment Protection Case is five milestones, and compressing any one moves the cost to inspection.
| Milestone | Days | Typical slip |
|---|---|---|
| Drawing and tooling | 5 | Redraws, three rounds |
| Resin and masterbatch | 7 | Special colours need volume |
| Moulding | 8 | Cavity queue behind other orders |
| Foam and hardware | 5 | Foam tooling unfinished |
| Packing and loading | 5 | Cartons arrive late |
One 40HQ holds 320 units. Inspect on loading day and concession is the only route, so gate inspection after assembly with three days behind it.
Add a penalty ratio and a list of extensions, such as redraws or resin rising past 3%.
5. Payment terms and three sources of a low price
Payment runs 30% deposit, 60% against the bill of lading, 10% retention. Thirty extra days adds 1.5% to 2.5%.
A low Equipment Protection Case price comes from one of three places:
- Regrind: 8% cheaper, impact down a third, pitting on the surface
- Thin walls: 4.2 mm cut to 3.6 mm, resin saved and stack margin lost
- Deferred charges: tooling billed again next order, packing by volumetric weight
None of it appears on the quote, so make resin grade, wall thickness and packing method contract annexes.
Buying an Equipment Protection Case is not a hunt for the lowest number.
Conclusion
Quotes for the same Equipment Protection Case differ because the five lines are split differently, not because the box changes shape. Match resin, moulding, tooling, hardware and freight, then settle mould ownership, tiers, milestones and terms. Do that and 38% narrows to something defensible. Buyers who read the split never haggle over an Equipment Protection Case.
This article discusses only the container (case body) side of specifications and design intent, and does not cover any handling, loading or use of the contents.
Related Reading
- Three lines of defence in an equipment case
- Choosing an equipment case by load and route
- Scoring a case supplier on one sheet
- How rotational moulding shapes case cost
Related Products
- 8 Series — Gun Cases; Military Equipment Cases; Camera Equipment Cases; Drone Cases; Watch Cases; Knife Cases; First Aid Cases; Electronics Equipment Cases
- WL8-2812 PP Gun Case — model WL8-2812
- All protective cases and toolboxes: 7 series, 158 models