Quick answer: Send one drawing to three suppliers and quotes spread by 30 %. The gap is rarely the shell; it sits in how the quote splits, how tooling is amortised and how lead time is built. Price a Fuze Pack Assembly per unit plus rework.
Table of contents
- Five Lines, Not One Price
- MOQ and Who Owns the Tool
- Where the Twenty-Five Days Come From
- Five Samples, Three Stations
- Payment Terms and the Rework Bill
- FAQ
1. Five Lines, Not One Price
A Fuze Pack Assembly quote carries five lines: shell, liner and locating parts, assembly labour, testing and packing, tooling. Four move with volume, the fifth does not.
| Line | Usual basis | What to check |
|---|---|---|
| Shell | Per set, colour master and trimming included | Wall tolerance stated, ribs priced separately |
| Liner | By weight or by pocket | Density quoted as nominal or as a measured band |
| Assembly labour | Minutes times a rate | Whether it absorbs rework |
| Testing and packing | Per batch or per set | Test items listed, third-party report or in-house |
| Tooling amortisation | One-off or folded into the unit price | How many sets, and whether the price drops after |
Two traps hide in the middle. A liner priced by weight moves several yuan a set when density swings 0.02 g/cm³, and the drawing says only as drawn. Testing folded in without a list returns as extras.
Re-sort a Fuze Pack Assembly quote first; the lowest total is usually the thinnest amortisation.
2. MOQ and Who Owns the Tool
Two hundred sets matches one clamp-up and one heat cycle. A tool needs two or three shots before a good part drops, scrap landing in batch one. Below that the supplier lifts the price or thins the wall.
Tooling at 42,000 is paid outright, folded into the price, or billed against volume. Outright is cheapest per unit but needs an ownership clause. A folded deal needs two lines often missing: how many sets carry the amortisation, and whether the price steps down.
Paying for a tool is not owning it. Write the transfer trigger, the stamp number, who repairs.
3. Where the Twenty-Five Days Come From
Twenty-five working days is four stages plus two days of buffer, not a promise.
- Material, 4 days: shell and liner resin land together, colour sampled
- Rotomoulding, 9 days: two cold shots, first-article sign-off, oven at 260 °C
- Foaming, 6 days: liner cures 24 hours, cut samples kept
- Assembly, 4 days: latches, hinges and labels in series
Only two places compress: the cold shots and the cure. Squeeze the first and yield drops; squeeze the second and the liner springs back.
4. Five Samples, Three Stations
Five samples, not one. Sample one carries cold-shot marks, sample five the steady state. One sample is the one they picked.
Two days covers three stations. The arm: temperature logs and the mould stamp, which must match the quote. The foaming bay: rack levels and cut samples, since an under-cured liner shows coarse cells. The bench: a preset torque driver.
5. Payment Terms and the Rework Bill
Sixty days on a Fuze Pack Assembly adds about 1.5 %, the cost of capital. Keep it separate.
| Rework item | Cost per set | Usual trigger |
|---|---|---|
| Liner replacement | 42 | Pocket out of tolerance, weak rebound |
| Latch replacement | 18 | Cracked body, torque overrun |
| Label reprint | 6 | Batch number does not match the case |
| Scrapped case | 260 | Lid seam leak, split corner |
The cheap quote saves three ways: thinner liner, another latch brand, carton instead of crate. A little from each and the unit price drops 3 %, about 5 a set. The rework rate climbs from 1 % to 4 %; three points at 42 is 1.26, so it still looks 3.74 ahead.
The real gap opens on the first return. Two hundred sets go back, the loading plan slips five days, storage runs 800 a day. Three returns a year and the saving is gone. That is the figure to sit beside the price. Add one return's downtime and the cheapest quote usually stops being cheapest. Ask for the rework rate in writing.
Conclusion
Buying a Fuze Pack Assembly is not a price comparison. It is five lines pulled apart, an ownership clause, a lead time by stage, a rework cost per unit. Do those four and the lowest quote stops being cheapest. What decides unit cost is how many days one return takes to recover, and a Fuze Pack Assembly contract should pin that down.
This article discusses only the container (case body) side of specifications and design intent, and does not cover any handling, loading or use of the contents.
Related Reading
- Judging a Fuze Pack Assembly: verdicts and rejects
- Scoring a case supplier
- How rotomoulding sets wall thickness
- A one-day factory walk-through
Related Products
- 8 Series — Gun Cases; Military Equipment Cases; Camera Equipment Cases; Drone Cases; Watch Cases; Knife Cases; First Aid Cases; Electronics Equipment Cases
- WL8-2812 PP Gun Case — model WL8-2812
- All protective cases and toolboxes: 7 series, 158 models