1. How OEM Plastic Cases for Electronics Are Quoted

OEM plastic cases for electronics look like one unit price, but six lines sit behind it. Quotes of CNY 96 and CNY 128 for the same drawing usually differ in tooling amortisation: over 3,000 pieces the mould adds CNY 12.7 each, over 300 it adds CNY 127.

Moulding depends on resin grade, part weight and press tonnage. Copolymer and homopolymer PP differ twofold in cold impact, 40 g of extra weight costs CNY 0.35, and a 600 × 450 × 250 mm case runs a 55-second cycle on 1,000 tonnes. Routed EVA at 30 kg/m³ costs CNY 18 per set; a nylon latch, CNY 6 to 9 per pair.

Cost lineShareDriver
Moulding38%Resin, wall
Tooling12%Amortisation base
Foam insert18%Routed or laminated
Hardware11%Latches
Packaging9%Printing
Testing12%Test scope

2. Minimum Order Quantity and Real Capacity

MOQ for OEM plastic cases for electronics comes from cavity count, press tonnage and changeover, not from a catalogue. A single cavity makes 1,440 pieces a day, so 300 pieces is four hours of running: four hours of changeover plus 30 pieces of settling scrap set the break-even point.

OEM plastic cases for electronics in white and blue, open, dark foam in the lid, two handheld devices, three silver cells, blue handle
OEM plastic cases for electronics in white and blue, open, dark foam in the lid, two handheld devices, three silver cells, blue handle

Check three documents, not a monthly output claim: the press tonnage list, cavity count per tool, and current schedule. If they disagree, the delivery promise has no basis.

Case sizePressMOQTooling
400 × 300 × 150 mm650 t300CNY 26,000
500 × 400 × 200 mm800 t300CNY 32,000
600 × 450 × 250 mm1,000 t500CNY 38,000
800 × 600 × 350 mm1,600 t500CNY 65,000

3. Tooling and Sampling Timeline

Allow 30 days for tooling: five of design, seven for the mould base, fifteen for machining, three for T1. Rework runs five to seven days a round, usually two rounds, first sink marks and flash, then fit.

Sampling has three routes: a 3D print in seven days for appearance only, a CNC sample in ten that survives a 1.2 m drop, a T1 moulded part in 30 that is the real article. Freeze the drawing with 1.5 degrees of draft and rib roots at 0.6 times the wall.

4. Lead Time and Inspection Milestones

The 25-day run splits into five days of material, twelve of moulding, four of foam, four of assembly. Foam is compressed first because routing can be outsourced, moving pocket tolerance from 0.5 mm to 1 mm.

OEM plastic cases for electronics, black corner close-up, grained shell, a black seal running along the rim, dark foam holding a glossy black panel
OEM plastic cases for electronics, black corner close-up, grained shell, a black seal running along the rim, dark foam holding a glossy black panel

Inspect at T1 for cavity size and latch alignment, at the 100-piece pilot for fit and drop, and at mass production with AQL 1.0 major, 2.5 minor. Colour stays within Delta E 1.5, dimensions within 0.3 mm, and no flow mark exceeds 2 mm.

StageDaysDeliverable
Drawing approval32D drawing, colour chip
Prototype73 samples
Tool build30T1 parts
Pilot run10100 pieces
Production25Inspection report

5. Five Clauses for the Purchase Contract

Five clauses matter more than price: tool ownership, amortisation method, late delivery penalty, inspection standard, and tool life. Write down where the tool is stored and who owns it if cooperation ends.

State the quantity at which amortisation stops, attach AQL values and tolerance bands, and rate tool life at 300,000 shots with notice before refurbishment. Sign a first-article sample, dated and kept by both sides.

Conclusion

Buying OEM plastic cases for electronics comes down to three habits: read the quote as six lines, calculate MOQ from changeover cost, and check lead time against four production blocks. With amortisation base, inspection points and tool ownership written down, the same supplier can carry the next batch of OEM plastic cases for electronics.

This article discusses only the container (case body) side of specifications and design intent, and does not cover any handling, loading or use of the contents.