Quick answer: A plastic tool box is priced from six cost blocks: resin, mould amortisation, moulding, assembly, packing and landed charges. Order quantity follows cavity count and changeover cost; lead time needs four signed milestones.

Table of contents

  • What a Plastic Tool Box Quote Is Made Of
  • How Order Quantity Is Set by Cavities and Changeover
  • Lead Time Split Into Four Signed Milestones
  • Acceptance Clauses to Fix in the Contract
  • Hidden Surcharges in a Price Comparison
  • FAQ

1. What a Plastic Tool Box Quote Is Made Of

A quote arrives as one number. Ask for six blocks: resin, mould amortisation, machine time, assembly, packing, freight and tax.

Resin is checked by weight. A 380 × 260 × 150 mm body with a 1.35 kg shot in PP at 9,800 CNY per tonne carries about 13.2 CNY of material; with 2% masterbatch and 3% regrind, quote 1.42 kg.

LineBasisRangeVerify
ResinWeight × price13–16 CNYRegrind
Tool spreadTool ÷ volume4.2 CNYStop volume
MouldingRate ÷ output95–130 CNY/hCavities
AssemblyPiece rate0.8–1.5 CNYManual
PackingPer carton1.1–2.0 CNYTest
FreightPer shipment13% VATLanded terms

Amortisation hides double charging: a 42,000 CNY tool over 10,000 units adds 4.2 CNY per piece, and charging it again at 30,000 units collects it three times. Fix the stop volume and the tool owner.

2. How Order Quantity Is Set by Cavities and Changeover

A minimum quantity falls out of cavity count, changeover time and the resin supplier's bag size.

Plastic Tool Box, Portable: sky blue case standing upright, one-piece top handle, two vertical ribs on the front, two feet below, matte texture
Plastic Tool Box, Portable: sky blue case standing upright, one-piece top handle, two vertical ribs on the front, two feet below, matte texture

A 1×2 cavity tool on a 380-tonne press at a 48-second cycle yields 150 shots an hour, 300 boxes; a 20-hour day reaches 6,000. A colour change costs two hours of cleaning, 8–12 kg of purge and a dozen tuning shots, so a 500-piece release ends before the barrel stabilises yet eats a changeover slot.

The answer is a framework contract: the 500-piece trial carries an 800–1,500 CNY setup fee, credited against the 5,000-piece run.

3. Lead Time Split Into Four Signed Milestones

"Thirty days to ship" means nothing alone. Split it into tooling, trial, production and inspection.

Tooling takes 18–25 working days once the drawing freezes, the trial two more. Modification and sample approval run five to seven days: a shot at 2.65 mm against a 2.8 mm drawing means cutting steel and trialling again. Approve samples on an ultrasonic gauge at twelve points.

Production runs 12–18 days from the signed first article, inspection three more, and freight adds 28–32 days from Ningbo to Hamburg, or 38 when space tightens. A 20ft container holds about 620 boxes.

4. Acceptance Clauses to Fix in the Contract

Price does not decide a project; acceptance does. Write limits a gauge confirms: AQL 2.5 appearance, colour inside ΔE 1.5, latches surviving 5,000 cycles, a 1.2 m drop on six faces without cracking, a 25 kg handle load without rivet movement.

Plastic Tool Box, Portable: white lid on a clear body, a narrow groove along the edge, one tabbed snap latch, shallow vertical ribs
Plastic Tool Box, Portable: white lid on a clear body, a narrow groove along the edge, one tabbed snap latch, shallow vertical ribs

Tooling terms belong in the same annex: 300,000 shots of cavity life before review, buyer ownership, and transfer or residual buyout at agreed volume.

5. Hidden Surcharges in a Price Comparison

Five quotes on one drawing spread 18% to 30%. The gap sits less in machine time than in charges that appear after ordering.

SurchargeTriggerAmountCounter
Small batchBelow 500800–1,500 CNYBundle
Custom colourNon-standard1,200 CNYStandard card
DecorationPrint, foil0.6–1.2 CNYMerge artwork
PackingBag, carton1.8–3.0 CNYShared carton
ExpeditedWeek cut8–15%Order earlier
TestingDrop, material1,500–3,000 CNYCover models

Payment terms move the price too: 30% deposit with 70% against the bill of lading lands 1.5–2% below prepayment, while 60-day terms add about 3%.

Quote validity matters too. PP moves 400–700 CNY per tonne monthly, so an expired 30-day quote can return 2% higher. Index the resin component to a public price and reset quarterly.

Conclusion

Negotiating a plastic tool box means turning one unit price into six auditable blocks. Check where amortisation stops, cost the changeover loss, date each stage, and write acceptance as numbers a gauge confirms. With those fixed, quotes become comparable, which is what a plastic tool box programme demands.

This article discusses only the container (case body) side of specifications and design intent, and does not cover any handling, loading or use of the contents.