Quick answer: What Information Is Needed for an Instrument Case Quote starts with six numbers: outside length, width and height, cavity length, width and height, plus one line on what goes inside. With all six a plant can weigh material, size the tool and price the same day; one missing and the number is a guess that moves within three days. Insert data, quantity layers, terms and fees only sharpen a price that already exists.

Table of contents

  • Six Dimensions to Give Before a Price
  • Drawing or Physical Sample: Which Quotes Faster
  • How Quantity, Lead Time and Terms Move Unit Price
  • Sample Fee, Tooling Fee and Amortisation
  • Fields a Complete RFQ Should Carry
  • FAQ

1. Six Dimensions to Give Before a Price

A slow quote is eight times out of ten a missing dimension on the RFQ, not a slow factory. The six are two sets of three — outside length, width and height, and cavity length, width and height. The gap between them is wall, base and lid depth, the numbers behind shot weight and press size.

Outside dimensions set tool size and clamp force, and come first in What Information Is Needed for an Instrument Case Quote. Give the cavity alone and the plant adds wall and rib itself; a 3–5 mm error moves the tool a price band.

DimensionDefinitionUsual omissionWhat it distorts
Outside lengthIncluding hardware bossesBody only, latches ignoredTooling underquoted
Outside widthIncluding handle overhangHandle left outWrong press tonnage
Outside heightClosed, feet includedConfused with open heightMaterial estimate
Cavity lengthClear floor lengthCorner radii ignoredInsert relayout
Cavity widthClear floor widthRib bosses ignoredPockets will not fit
Cavity heightClear depth under lid foamNominal depth usedLid fouls instrument

Usable height is often forgotten: subtract lid foam and base pad and clear space runs 10–20 mm short of the drawing. Keep one unit throughout and say whether the case stands or lies down, since that decides the handle root — a small point, but part of What Information Is Needed for an Instrument Case Quote all the same.

2. Drawing or Physical Sample: Which Quotes Faster

Whether a drawing or a sample answers What Information Is Needed for an Instrument Case Quote faster is a matter of two or three days. A DXF layout or a dimensioned PDF reads clearly; a sample tells the truth about awkward shapes. Send both: one to price, one to check.

What Information Is Needed for an Instrument Case Quote black case closed at low angle, twin latches and purge valve centred
What Information Is Needed for an Instrument Case Quote black case closed at low angle, twin latches and purge valve centred

With a drawing alone, name the foam: EVA or PU, density 45–80 kg/m³, hardness 25–40 Shore. Material shifts toolpath speed and scrap by 10%–15%, and the price follows.

With a sample alone the plant measures, scans and redraws, costing 2–3 days but holding pocket tolerance near ±0.2 mm. Kerf needs saying: routing leaves 3–5 mm, too much and the instrument rattles, too little and it will not seat.

A deeper insert forces a deeper shell: 30 mm of EVA instead of 20 mm drops clear height 10 mm, meaning a new lid, not a new insert — one more line for What Information Is Needed for an Instrument Case Quote.

3. How Quantity, Lead Time and Terms Move Unit Price

Quantity is the next block of What Information Is Needed for an Instrument Case Quote, and it comes in three layers: first order, single release, annual volume. "A few thousand a year" pushes the plant to its smallest batch and highest step.

Lead time: 25–35 days from deposit to dispatch, trials and first article included; 15 days usually adds 10%–20%.

TermWhat the price coversFrequently missed
EXWFactory gate onlyPallets and packing
FOBInland freight, clearance, loadingTerminal and document fees
CIFAdds ocean freight and insuranceDestination charges

Across the three the gap runs 8%–12%, so compare on one basis first. Payment terms belong here too: 30% deposit with balance against the bill of lading, or full prepayment, is worth 2%–3%.

Volume steps need a definition too, and they are the part of What Information Is Needed for an Instrument Case Quote written last: priced on the order, or rebated on the annual total with a stated rate and cycle. Without that line, the second year opens with a dispute.

4. Sample Fee, Tooling Fee and Amortisation

Two payments, two logics: the sample fee buys pieces, tooling buys capacity, and their refund rules share nothing — which is why What Information Is Needed for an Instrument Case Quote splits them.

Sample fees run 800–2000 RMB per unit for three to five units, routing and printing included. Most plants refund the fee past 100 units when the clause allows.

Tooling for a mid-size shell is 80,000–150,000 RMB per set, written one of three ways: charged once, amortised per unit, refunded at volume. Amortised tooling needs a ceiling, usually recovered over 500–1000 units; refunds need a trigger and a date.

Post-mould changes are separate: a moved pocket, an added port or a reshaped latch costs 2000–8000 RMB by area. Settle title and relocation terms before the contract meeting.

5. Fields a Complete RFQ Should Carry

What Information Is Needed for an Instrument Case Quote ends up as a one-page table, not a paragraph in an email.

What Information Is Needed for an Instrument Case Quote pale grey side panel detail, one-piece radius and handle root against dark
What Information Is Needed for an Instrument Case Quote pale grey side panel detail, one-piece radius and handle root against dark

Five groups cover it: product (name, use, six dimensions, wall), insert (material, density, layout), appearance (colour, print position), commercial (quantity layers, lead time, terms, port), quality (acceptance, packing). Between them they answer What Information Is Needed for an Instrument Case Quote completely.

GroupMust fillCommon mistake
ProductName, use, six dimensionsCavity dimensions only
InsertMaterial, density, layoutKerf left unstated
AppearanceColour, print positionLogo sent as a picture
CommercialQuantities, lead time, termsAnnual volume only
QualityAcceptance, packingSampling level unset

Three optional lines help: target price, acceptable alternatives, last purchase price. A target price lets the plant adjust wall and insert grade instead of quoting its standard build. Attachments belong on the same page, because half of What Information Is Needed for an Instrument Case Quote arrives as files.