Quick answer: Price a Hand Tools Case as six lines, not one number: material, moulding, tooling amortisation, hardware, packing, freight and duty. Then put MOQ, tooling ownership, lead time and rework liability into the contract.

Table of contents

  • Why a Hand Tools Case Quote Is More Than a Unit Price
  • MOQ and Tooling Ownership: Who Pays, Who Owns
  • How the Lead Time Is Actually Built
  • Four Costs That Slip Off the Quote
  • Payment Terms, Factory Visits and Penalties
  • Cost Per Case Over Three Years
  • FAQ

1. Why a Hand Tools Case Quote Is More Than a Unit Price

Three suppliers quote 62, 68 and 75 yuan; most buyers call the 62 first. What matters is what sits inside the number: tooling excluded, packing billed at 3.5 yuan a case, quote ex-works, freight 4.8 yuan on arrival.

Quote lineHow suppliers write itWhat to pin down
MaterialBy gross case weightResin grade, regrind ceiling
MouldingOne price per caseCavities, cycle time, scrap owner
ToolingSeparate or amortisedAmount, instalments, ownership, transfer
HardwareLatches, hinges, handle in or outBrand, material, spares
PackingUsually per caseBoard grade, carton count, pallets
Freight and dutyEx-works or deliveredDelivery point, payer, tax

Unit price is one line out of six, and once all six are added the 62 yuan case is often the dearer one; the same drawing can return different wall sections.

2. MOQ and Tooling Ownership: Who Pays, Who Owns

An injection mould for a mid-size Hand Tools Case runs about 86,000 yuan, and how that sum is spread sets the first batch prices.

Hand Tools Case: orange case open on a wooden bench, empty black foam pockets, two front latches, grey bin racks behind, shelving and lathe beyond
Hand Tools Case: orange case open on a wooden bench, empty black foam pockets, two front latches, grey bin racks behind, shelving and lathe beyond

Suppliers quote three tiers: 500, 1,500 and 3,000 pieces. Unit price falls with volume, tooling amortisation moves the other way.

Order sizeUnit priceTooling per caseLanded cost incl. packing
50078 yuan172 yuan258 yuan
1,50072 yuan57.3 yuan137.3 yuan
3,00068 yuan28.7 yuan104.7 yuan

At 500 the mould exceeds 60% of landed cost, so many small orders use a stock mould.

Tooling ownership needs four clauses: who pays, where it lives, whether it leaves at order end, who scraps it. Pay without ownership and the next supplier cannot run it.

3. How the Lead Time Is Actually Built

Lead time is five stages in series. Compress one and pressure lands on the last.

  • Sampling: 7 days, including foam layout and colour approval.
  • Trial shot and tool correction: 15 days, usually two rounds of gate and cooling changes.
  • First article: 3 days, key dimensions plus latch closing force.
  • Production: 30 days of moulding and assembly, 500 to 3,000 pieces.
  • Transport: 35 days by sea or 5 days by road.

The first four add up to 55 days from drawing approval to warehouse. A supplier promising 30 has counted sampling as done.

4. Four Costs That Slip Off the Quote

The unit price is settled; the account is not.

Hand Tools Case: orange lid fully open with moulded pockets, foam tray of open-end wrenches and an orange meter, wrench-covered pegboard, grinder at left
Hand Tools Case: orange lid fully open with moulded pockets, foam tray of open-end wrenches and an orange meter, wrench-covered pegboard, grinder at left
Hidden costTypical rateTrigger
Rework and sorting4.2 yuan per caseLoose latches, offset pockets; 8% of 1,000 is 336 yuan
Packing upgrade1.8 yuan per case, 60 per palletThree-ply to five-ply board, pallet and wrap
Tool modificationFrom 3,000 yuan per changeColour change, revised pocket layout
Testing and reportsAbout 1,200 yuan each48-hour salt spray, drop video, material test

Together these often exceed two points of unit price; lock them at negotiation.

5. Payment Terms, Factory Visits and Penalties

Pay 30% deposit, 60% before shipment, 10% after incoming inspection. Paying in full looks simple until a delay leaves you no leverage. Aim for 60-day terms, provided the supplier can carry the cash. Below 30 days, small plants price the capital cost back in, so the term you won looks like interest paid early. Penalties of 0.3% a day, capped at 10% of contract value, cover lost output without pushing a supplier to walk away. That clause matters most with small plants.

Budget two person-days for a factory visit: press tonnage and cavity count against the quoted cycle, regrind segregation, first-article samples.

6. Cost Per Case Over Three Years

68 yuan is a start. On 3,000 pieces across three years: 68 yuan material and moulding, 28.7 yuan tooling, 8 yuan packing and freight, 4.2 yuan rework reserve, so 108.9 yuan a case. Placing all 3,000 at once trims another 6 yuan.

Reverse it: if the 62 yuan box has latches lasting two years, three years needs 1.5 replacements and spend passes 130 yuan a case.

Conclusion

A Hand Tools Case never has one purchase price; it has conditions. MOQ decides tooling spread, milestones decide who carries delay risk, rework decides the third-year cost. Align the six quote lines, put tooling ownership in the contract. The contest is not five yuan but who counts total cost honestly.

This article discusses only the container (case body) side of specifications and design intent, and does not cover any handling, loading or use of the contents.